Urban Garden/2nd Street Construction

Starting Wednesday March 4th, HDCC will drive pilings within the University of Hawaii Urban Garden along 2nd Street. This work will start with 18 piles driven along the waterline route for field analysis. Once all testing has been concluded, full construction will commence in the same area.

The current timeline/schedule for this work is as follows:

* Test Piles Driven: March 4th – March 20th

* Testing/Analysis: March 21st - Late April

* Full Construction/Pile Driving: Late April - Winter 2021

If you have any questions, please contact us