Project Schedule



As we begin the holiday season, HDCC continues to make progress on various aspects of the project.


* Work continues in the cul-de-sac at the top of Waihona Street and near the Hawaii Business Park.


* HDCC will also be continuing work in the UH Garden and on 2nd Street for installation and testing.


* Starting Friday, installation work will begin in the median of Kamehameha Highway near Sam's Club. The work is scheduled for approximately 1 month.


In observance of the holidays, the project will be shut down the following days:


November 25th, 2021

November 26th, 2021

December 24th, 2021

December 31st, 2021


Please contact us with any questions.