Project Schedule
As we begin the holiday season, HDCC continues to make progress on various aspects of the project.
* Work continues in the cul-de-sac at the top of Waihona Street and near the Hawaii Business Park.
* HDCC will also be continuing work in the UH Garden and on 2nd Street for installation and testing.
* Starting Friday, installation work will begin in the median of Kamehameha Highway near Sam's Club. The work is scheduled for approximately 1 month.
In observance of the holidays, the project will be shut down the following days:
November 25th, 2021
November 26th, 2021
December 24th, 2021
December 31st, 2021
Please contact us with any questions.