Project Updates
HDCC continues to work in multiple project areas along the project route. HDCC's project areas are:
University of Hawaii's Urban Garden/2nd Street - The last few piles coming out of the Urban Garden have had some delays. The work along 2nd Street is now scheduled to begin the week of March 15, 2021.
Top of Waihona Street's Cul-De-Sac - Continuation of waterline work will begin at the top of Waihona Street near Sandwich Isle Pest Solutions. This work will last into the Summer.
Manana - HDCC will be back in Manana Housing the week of March 15, 2021. This work will be done outside of the roadway and should have minimal impact to the area.
Waihona Street - Utilities continue to be relocated along Waihona Street to accommodate the placement of the waterline. Paul's Electric will be in the vicinity of HDCC's Waihona Street Field Office to do the final relocation in the near future. The work is scheduled for approximately 1 month.
Please contact us with any questions.